Sheet piles to be installed next winter
Joe McWilliams
Lakeside Leader
Slave Lake’s airport property took a hit from high lake water back in 2020. About 40 feet of property at the west end of the airport was chewed up when high water, plus strong west winds, caused severe erosion.
Ever since, the Airport Services Commission has been trying to figure out how to prevent further property loss, without breaking the bank. Various schemes were suggested, and then rejected as being unaffordable.
But now, according to Airport Manager Pierre Gauthier, the province has stepped up with a grant. The plan at this point is to install sheet piles. The estimated cost is about $1.4 million. With the 70/30 cost split, the commission would be on the hook for about $400,000, Gauthier says.
That of course assumes a contractor can be found to do the job within the budget.
The stabilization has to happen. Gauthier says there’s a certain distance (60m) that has to be maintained between the end of the runway and the end of the airport property. At one corner, there’s only 1.7 metres of leeway left between that threshold and the lakeshore, since the 2020 erosion, he says.
Luckily, the lake has been mostly low since then, but that could change any time. Gauthier calls the situation, “a bit alarming.”
If that final 1.7 metres was lost, “we’d have to shorten the runway.”
An earlier plan had rock bags being installed to keep the waves at bay. But that was ruled out due to the rules around archaeological sites. The land along the lake there has such a designation, as it was a fur trade outpost, back in the day. The sheet piles get around that restriction, Gauthier says, because of how much less space they take up.
Gauthier says the project has “been in limbo, waiting for money,” but can now go ahead. What happens now, he says, is it goes back to the engineers for design. Environmental approvals are already done, but the earlier design work was for the rock bags, so with the new sheet pile proposal, there’s some work to do there. Gauthier says the expectation is the installation work will be done next winter.