Phase I of the conversion of the old Slave Lake fire hall on Caribou Trail into the new ambulance (EMS) facility commenced recently. Alberta Health Services isn’t calling it ‘construction,’ yet. That is expected to start in April and finish sometime this summer. What’s going on now is demolition in preparation for construction.
Slave Lake EMS has been operating out of cramped quarters in the Health Complex for many years. About a year ago, AHS bought the building from the town and announced the conversion with a $4.7 million budget. That has since grown to $6.8 million. One reason for the higher cost, says an AHS spokesperson, is more asbestos than expected has been discovered in the demolition process
Delnor Construction is the contractor.