Pearl Lorentzen
Lakeside Leader

On July 9, 2024, Town of Slave Lake council agreed to renovate the Multi Rec Centre with a vote of four to three, with Mayor Francesca Ward, Deputy Mayor Shawn Gramlich, and Councillor Ali Mouallem opposed.

This is a relatively small renovation to add two more offices to the lobby of the MRC. The budget is $150,000. These will be on either side of the reception desk and the two offices already in the lobby. During construction, the town will also add the proper heating and AC to the offices, plus sprinklers. The idea is to move one or two of the supervisors that manage this building and the Legacy Centre out of the Town of Slave Lake office and into the MRC.

“This is the best use of the space,” said Joe Dixon, Director of Community Services. Administration had looked at various other options, which were much more expensive and not as practical.

Council had agreed to this capital project back during budget, but was less inclined now.

Deputy Mayor Gramlich and Councillor Mouallem were concerned that removing some lobby space would make the MRC less attractive for the Treaty 8 and other large hockey tournaments.

“I didn’t want to use open space,” said Deputy Mayor Gramlich.

“I haven’t seen obsessive use of these spaces,” argued Councillor Steve Adams.

“This space is relatively unused,” said Dixon. The lost and found will be moved to a new location from one side and a gum ball machine and Royal LePage sign from the other. It doesn’t interfere with viewing area.

Mayor Ward was unsure of the need the project.

Proper heating, cooling, and fire suppression are “a huge need,” said Councillor Kim Hughes.

Dixon also explained that the current set up isn’t efficient. For example, the staff can’t sit at the computer while talking to clients because of cabinets. The renovations will fix this, but he did not see a connected between adding the offices and improve customer service, which was one of the stated goals for the project.