Rentals to resume in late July, says town

Joe McWilliams
Lakeside Leader

Eighteen hours without power in the southwest part of Slave Lake last week was too much for the ice in the Multi Rec Centre. A bit less than that and it might have been saveable, says head ice maker Wayne Bacon, but so it went.

The failure, which happened late in the first week of June, was the second of two major outages (that we know of) that hit Slave Lake that week. Power was out in a large part of the southeast part of town for about five hours on the Thursday evening. A couple of days later, the southwest got hit.

As for the cause, or causes…..ATCO Electric says both outages (they were unrelated) were likely caused by something that happened underground.

“Specifically,” says ATCO’s Doris Kaufmann Woodcock in an email to The Leader, “melting frost, ground shifting and rainfall can all play a part in causing faults to our system.”

The loss of ice is more than an inconvenience for Slave Lake’s Summer Rec hockey program. Organizer Mike Martin said on June 10, “as of today, Summer Rec will be canceled going forward,” and promised refunds.

“We are disappointed,” Martin told The Leader in an email, “and hopeful(ly) it goes back in ASAP.”

Town councillors had questions on the situation and got answers from the town’s new community services director Joe Dixon at council’s June 11 meeting.

One thing Dixon was asked was why the estimated date for resuming operations was at the end of July. That’s almost two months, observed Councillor Brice Ferguson.

That’s a worst-case scenario, Dixon said.

“The last thing I wanted to do is provide a timeline we couldn’t deliver.”

Dixon added it was more likely the ice would be ready for use by mid-July. It could have been even earlier, but as rentals were light, the town decided it would be a good time to do some overdue pressure washing of the stands and painting. The temperature of the building needs to be high enough for that to work properly; hence the gap of about a month before starting to re-establish the ice in Arena #1.

Dixon said the town would also be using the down time to do other necessary maintenance – to the sound system, for example.

“I think, with a bit of patience, we’ll see a much better facility,” he said.

Dixon also provided information about renting a generator, or generators, for backup purposes, complete with technical complications and costs.

Councillor Shawn Gramlich didn’t like what he was hearing on the generator costs.

“I think there are maybe cheaper options,” he said, citing related experience from the oilfield.

Getting back to ATCO and what it is doing about what appears to be the increasing frequency of such outages (this was mentioned at the council meeting as well), construction methods have improved, Kaufmann Woodcock says. With modern methods, underground lines are much less susceptible to damage. Overhead systems are also being improved, she adds.

“We thank customers for their patience over the last few days, and apologize for the inconvenience.”