Chastin Martel
Lakeside Leader
There is a new way of installing ice at the Multi Recreation Centre (MRC), thanks to a new method called the ‘easy sheet process.’ It cuts down the ice install time from days to just hours. Here to explain the process and provide more insight on it is Calvin Beauchamp, manager of facilities and parks for the Town of Slave Lake.
How the new process works is below all the ice are concrete slabs. These concrete slabs are topped with approximately a quarter of an inch of ice, says Beauchamp. Once ice is frozen, large digitally printed liners with the town’s logo and lines are added on top. These liners are printed in Edmonton.
The creases and lines are all reusable overlays, he says. After the liners are added, an inch of ice is added on top. Once the ice is removed, the white liner will be reusable for installs in the future. The whole process takes four to six hours with three to four staff members.
This process was an easy decision to make as the quick cost recovery had benefits, he adds. The recovery cost will take about three years. The cost savings include labour, the ice compressor running less, and on paint, utilities and disposal.
“From an environmental and financial standpoint, this should have a positive impact on our overall operations of the facility,” says Beauchamp.
The older process is similar to this new method but instead of laying a liner, it was painted with the exception of the overlaying the town’s logos.
These logos were the only reusable part, he says. This process took a group of six staff members three to four days to complete.
Asked if this new method changes how the ice is maintained, Beauchamp says, “This new installation process does not change how any ice maintenance is done and will not affect the overall ice quality.”
The town received a matching grant from Municipal Climate Change Action Centre (MCCAC) to switch to this new system in both arenas, he says. The town’s portion of the cost was approximately $37,000.
“This system has been used by some other arenas for up to 20 years using the same original liners,” he says.
“Not only has ‘easy sheet’ been used around the world in hockey rinks, it is also used in a lot of curling rinks including ours here in Slave Lake.”
Beauchamp tells The Leader that the ‘easy sheet’ process is gaining momentum for the reasons listed above. The town is always looking for innovative ways to make improvements with the facilities.
“This project should have an overall positive impact,” he says.