Slave Lake’s trash rack has taken quite a beating over the years, but it was designed to, and 30-odd years after it was installed it continues to get the job done. It is located a kilometre or two south, or upstream of town.

The Government of Alberta built the big fence after the 1988 flood that swamped much of the southeast and part of the northeast sections of town, including the hospital. One of the aggravating factors in that flood was all the floating debris that clogged up the flood channel where it passes under Hwy. 88. This caused the water to back up and overflow the berm into the southeast.

The response had two main parts. One was building the trash rack to keep the flood debris out of town; the other was to raise the berm along the north edge of the diversion channel. There have been many high water events since then, but the racks and the diversion have worked well to keep the water within its banks.

In the meantime another flood risk study has been done for the creek and the town. It was published in January of 2023, by Golder Associates and is available online. At the same time, a government ‘flood mapping’ project is underway, and last week the Town of Slave Lake asked residents to take part in a survey on the topic. Specifically, the government is looking for feedback on the latest flood hazard maps (see below).

Such maps are used for planning purposes – both for development and emergency response. Information on the town’s flood mapping survey can be found on the Town of Slave Lake website or Facebook page.

Still standing: The trash rack across Sawridge Creek, upstream from town, as it appeared on Dec. 9.
The Town of Slave Lake is seeking public input on this map ranking areas by flood likelihood.